Box 5
Contains 57 Results:
Projects 4222-4236, 1939 December 7
Dry Grinding and Packing Building #4. Report by R. W. Fulling
Projects 4222-4519, 1939 December 21
Dry Grinding and Packing Building #4. Report by T. O. Rice
Mr. W. G. Ramsay, circa 1903
Mr. W. G. Ramsay, Central Engineer.
Acid Recovery House, circa 1903-1907
Acid Recovery Addition, Acid Recovery House.
Water Heater, 1912 January 12
Water Heater for mixing concrete in cold weather, cover on, cover removed. Photographs by W. D. Craig.
Outside Steam Lines, 1912 January 30-1912 February 29
Transformer Station, 1912 January 30-1912 May 18
Transformer House and Station, Switchboard, 22000 Volt line entering station. Photographs by F. A. Wheeless, W. D. Craig
Boiler House, 1912 February-1912 June 15
Boiler House Construction. Photographs by W. D. Craig.
Soda Bag Wash House, 1912 February 5-1912 June 15
Construction, Putting Tanks in Building, Soda Bag Washer. Photographs by W. D. Craig.
Panorama of Plant, 1912 March 18
Overhead views of Plant, separate photos similar to panorma. Photographs by W. D. Craig.
Corning Mil Motor House, 1912 May 18
Corning Mill Motor House Starter, General Electric Starting and Ovreload relay coils.
Powder Area, northeast and northwest views, 1913 November 27
Showing Powder Line Office Gelatine Change, View of Hand Pack House Spare Parts Machinery Storage Dynamite Change House Second for Shell House. Photographs by J. B. Jackson
Foundations, 1913 November 27
Combined Shops Foundation, Main Office Foundation, Pulp Dynamite Foundation. Photographs by J. B. Jackson
Laboratory and Acid Change House, 1913 November 27
Photographs by J. B. Jackson, Assistant Engineer
Ingredient Store House and Supply and General Store House, 1913 November 27
Supply and General Store Houses and Unloading Platform Pieces, Ingredient Store at Left, Supply and General Store at right. Photographs by J. B. Jackson
Views North, North West, North East and West, 1913 November 27-1914 February 3
View Looking North, View North East, View North West, View West. Photographs by J. B. Jackson
Soda Store House, 1913 November 27-1914 May
Showing Method of Concentrating Soda Store House (people pictured in), Soda Bag Store House. Photographs by J. B. Jackson
Unloading Crane and Driller at Well #12, 1913 November 27-1914 December 12
Photographs by W. B. Chamerlin and J. B. Jackson
Shell House, 1914 April 11
Rear and East End. Photographs by J. B. Jackson
Visitors, 1914 July
Visitors J. U. Bacchus, R. H. Durham, H. M. Pierce, and Wm. B. Chamberlin.
Grain Car Shed and Double Coal and Wood House, 1914 July 10-1915 January 28
Grain Car Shed - Corning Mill Foundations in Distance, Double Coal and Wood House. Photographs by W. B. Chamberlin, J. B. Jackson
Boarding House, 1914 September 15-1914 December 12
Photographs by J. B. Jackson, Assistant Engineer
Club House, Portland Cottage, Carolina Cottage, Hamilton Cottage, Detroit Cottage, Georgia Cottage, Amherst Cottage, Forsythe Cottage, Standard Cottage, 1914 December 12
Photographs by W. B. Chamberlin, Resident Engineer
Stable and Tennant House, 1914 December 12
Photographs by W. B. Chamberlin, Resident Engineer
Village, 1914 December 12-1915 January 28
Three Views of Village, Water Tank at Village under Construction. Photographs by W. B. Chamberlin, Resident Engineer
Nitre Cake Cars, 1915 January 28
Nitre is saltpeter (potassium nitrate). Photographs by W. B. Chamberlin, Resident Engineer
Well No. 5, 1915 January
Photographs by W. B. Chamberlin, Resident Engineer
Project 742-495, 1935 August 12
Attack Building #15.
Project 742, 1935 September 10
#2 Calciner, Filter Building #13, Attack Building #15, Shipping Building #4, Louisville Dryer, Office and Laboratory, First Aid and Process Laboratory, Tank Farm, Copperas Storage Building #12, Construction Shops,. Report by H. S. Stanton
Project 742, 1935 September 30
#1 Process Building, Building #3, Calciner, Feed Tank, Acid tanks, Louisville drier, #4 Building, Pump House, Storage Tanks. Report by H. S. Stanton
Project 742, 1935 October 21
Filter Building, Attack Building Tanks, Stedman Pan Building, Calciner, Tank Farm, Ilmenite storage #1, Wood Tank S-42. Report by H. S. Stanton
Project 742, 1935 October 23
Calciner Firing House, Ammonia Weigh House, Acid Storage Tanks, Tank Farm, Filter Building #13. Report by H. S. Stanton
Project 576 and 742, 1935 December 10
Building #4 Dry Grinding, Packing, Shipping, Acid Lines, Ammonia and acid Weigh House, Calciner Discharge House, Tank Farm, Filter Building #13, Steam Lines. Report by H. S. Stanton
Project 742, 1935 December 24
Filter Buiding, Tank Farm, Attack Building, Calciner, New Crystallizer #3.
Projects 2366, 1751, and 2496, 1937 September 29
Office and Shops, Pier, 2500,000 Gallon Storage Tank, Warehouse, Evaporating Building. Report and photographs by J. B. Sherts
Project 2366-2496, 1937 October 16
Concentraer, Evaporating Building, Warehouse. Report by J. B. Sherts
Projects 2366-1751-2774-2496, 1937 October 30
Evaporating Building, Storage Tank, Ilmenite Pile, Warehouse . Report by J. B. Sherts
Projects 2366-1751-2774-2496, 1938 January 29
Evaporting Building, Retaining Wall, Tank for Fire Protection and Pump House, Warehouse.
Project 4222, 4236, 1939 November 30
Piling Railraid Cars and Column Lines. Report by R. W. Fulling
Burner House, circa 1903-1907
Burner House Acid, Framework of Burner House.
Converter House, circa 1903-1907
Foundations for Slack at Converter House, Foundations of Slack at Converter House, Converter House.
Hand Packing House, circa 1903-1907
Hand Packing House #1, Heater House Hand Punching #1, Hand Packing House.
Nitroglycerin Gutters, circa 1903-1907
Nitroglycerin Gutter to Nitrglycerin Store House number 2, Nitroglycerin Gutters from House to House, Nitrglycerin Gutters from Nitroglycerin Plant to Nitroglycerin Store House.
Pyrites Bin and Trestle, circa 1903-1907
Pyrites Bin and Trestle, Pyrites Bin and Trestle Converter House and Burner House.
Suction Filters, circa 1903-1907
Foundation Suction Filters, Suction Filters.
Office, 1903 September 7
Office, Office-Sleeping Apartment and Private Camp.
Land and Buildings, 1903 September 7-1909 January 24
Sour Mill, Log Jam, Birds Eye View of Part of Powder Line Concluding Mixing House, Land, Cleared Land Leaving Hand Wood Evergreens and Stumps for Fire Protection, Wilderness, Stable Addition at Rear for Storage of Hay and Feed.
Houses, 1903 October 28-1909 March 1
Repairs to Power House Wall, Foundation Dynamite Mixing House, Foundation Separating House, #2 Powder Line from #2 Mixing House, Heater House #2, Blower House.
Case and Dip House, 1903 October 23-1904 January 29
Case and Dip House.
Lead Burner Shop, 1903 October 29-1904 January 29
Lead Burner Shop, Foundation Lead Burner Shop.