Box 3
Contains 51 Results:
Separating House, 1912 November 20-1919 December 31
Separating House Barricade, Rock excavation, Landslide progression, additions. Report by W. D. Craig and James H. Hutchison. Photographs by W. D. Craig.
Ammonia Plant Rebuilding, 1912 December 31-1913 March 31
Ammonia Plant Rebuilding. Report and photographs by W. D. Craig.
Ammonia Oxidation Plant, 1928 September 25
Converter and Absorption House, Weak Acid Weigh Tanks House, Ammonia Storage Tanks Foundations, Power House Addition Foundations, Engine Room Addition Fundations,. Report and photographs by P. I. Newman.
Ammonia Oxidation Plant, 1928 October-1928 November
Main Power House- Engine Room Addition, Weak Acid Storage Tank, Outside Acid Lines, Ammonia Storage and Unloading Platform,Converter and Absorber House. Report and photographs by P. I. Newman.
Engineering Corps, 1910
Photo of a group of men,. Photographs by W. B. F.
Supply and General Store, 1911 March 25-1911 April 25
Supply and General Store. Photographs by John Lee Pratt, R. E.
Standard Gauge Track Construction, 1911 March 25-1911 April 25
Location of Trestle on Grove Creek, Excavation, Pile Driving for Standard Gauge Track to Power House, Branches to Safety Plant and Magazines, track to Coal Trestle at Power House. Photographs by A. W. Copp , John Lee Pratt
Power House Construction, 1911 March 25-1912 February 27
Pit for Coal Trestle, Coal Storage, Coal Trestle, View, Main Power House, Brine Tank House, Brine Line, Engine Room View, Air Receivers. Report by D. T. Rice, R. E. Photographs by John Lee Pratt, J. Thompson Brown, D. T. Rice
The Spring, 1911 April 15-1912
Spring with a group of people, Barn at the Spring, Resevoir looking east. Photographs by A. W. Copp, D. T. Rice
Store Houses, 1911 April 16-1911 June 28
Store House, and View of Store Houses, Shops and Water Tower. Photographs by A. W. Copp, D. T. Rice
Offices, 1911 April 16-1911 August 26
Views from Office Hill, Boarding House, Engineering Department Office, Engineering Department Drafting Room, People: John L. Pratt, W. G. Ramsay, W. B. Foster, W. G. Rommel, E. S. Wilson, L. J. Darrel, Main Office with people in front. Report by A. W. Copp , D. T. Rice. Photographs by A. W. Copp , D. T. Rice
Powder Buildings Construction, 1911 April 16-1912 April 29
Site Selected for Location of Powder Buildings, Powder Line Office, Hose House and Pipe Lines. Photographs by A. W. Copp , D. T. Rice
Pulp Dry House Construction, 1911 April 25-1911 December 29
Foundation, Progress and Completion, Gun Cotton Store. Report by D. T. Rice, Resident Engineer. Photographs by John Lee Pratt, J. Thomspon Brown
Construction Projects, 1911 April 25-1912 February 21
Tramway Grading, Road Construction, Public road at Grove Creek, Snow Storm Effects. Photographs by John Lee Pratt, D. T. Rice
Shops Construction, 1911 April 25-1912 July
Combined Shops, Machine Shop- Pipe Machie showing Guards.
Storage Projects, 1911 April 25-1916 June
Ingrediant Store, Paraffine Storage, Lime Storage. Photographs by John Lee Pratt, D. T. Rice
Water Tank, 1911 April 30-1911 June 1
Foundation for Water Tank, Temporary Pump Unit. Report by D. T Rice. Photographs by John Lee Pratt, J. Thompson Brown,
Soda Store House, 1911 June 1-1912 March 29
Soda Store House, Soda Dry House, Nitric Acid Soda Tower, Soda Bag Store House, Soda Bag Wash House and Interior. Report by D. T. Rice, Resident Engineer. Photographs by D. T. Rice, J. T. Brown
Gelatin Mixing Construction, 1911 June 1-1912 May 30
Gelatin Cartridge Machine House, Gelatin Mixing House, Barricades for G. M. House, Barricade for Gelatin Cartridge Mixing House. Report by D. T. Rice, Resident Engineer. Photographs by D. T. Rice, Resident Engineer
Hall House Construction, 1911 June 1-1912 May 30
Foundations for Hall House #1, Motor House, Barricade for H. H. #1, Hall House #2. Report by D. T. Rice, Resident Engineer. Photographs by D. T. Rice, J. T. Brown
Dope House Construction, 1911 June 28-1912 March 29
Foundation, Construction Views, 2nd Floor Interior. Report by D. T. Rice, Resident Engineer. Photographs by D. T. Rice, Resident Engineer
Nitric Acid Plant Construction, 1911 June 1-1916 April 24
Foundations, Nitric Acid Building Absorption Tower Foundation, N. A. House, N. A. Recovery, Acid, Air and Steam Lines to N. A. Plant, Interior of of N. A. Recovery & House, Glass Acid Lines between Recovery and House, Salt Cake Shed, Addition to Nitric Acid House. Report by D. T. Rice, Resident Engineer. Photographs by J. Thompson Brown, D. T. Rice, H. N. Richardson
Shell House Construction, 1911 June 28-1916 July 24
Shell House and Shell Paper Store House. Photographs by D. T. Rice, Resident Engineer, W. H. Stevenson
Box House Storage Construction, 1911 August 1-1912 May 30
Box Store House, Packing House, Railroad Cut, Interior. Report and photographs by D. T. Rice, Resident Engineer
Dynamite Mixing house, 1911 August 1-1912 April 29
Dynamite Mixing House & Barricade. Report and photographs by D. T. Rice, Resident Engineer
Laboratory, 1911 August 26-1911 September 26
Laboratory Construction, Lab and Combined Shops in backgound. Report and photographs by D. T. Rice, Resident Engineer
Magazines #1 and #2 Construction, 1911 August 26-1912 May 30
Sites for Magazine 1 and 2, Magazine 1, Magazine 2. Report and photographs by D. T. Rice, Resident Engineer
Waste Acid Construction, 1911 September 26-1912 February 27
Waste Acid Store Foundation, Waste Acid Tower. Report and photographs by D. T. Rice, Resident Engineer
Ammonia Nitrate Housing Construction, 1911 September 26-1912 September 30
Ammonia Finishing House & adjacent buildings, Ammonia Liquor Storage, Ammonia Nitrate Distillation House, Interior Ammonia Distillation, Evaporating Shed and Settling Tanks. Report and photographs by D. T. Rice, Resident Engineer
Nitroglycerine House, 1911 September 26-1912 November 2
Foundation for Combined Nitroglycerine and Separating House, Combined Neutralizing and Nitroglycerin Store, Nitroglycerin and Seperating House, Nitroglycerine Gutter, Interior of Neutralizing and Nitroglycerine Store House, Mixed Acid Storage, Nitroglycerine House Barricades, Glycerine Heater House, Neutralizing & Nitroglycerin Store House, Shed for Salt and Addition to building. Report and photographs by D. T. Rice, Resident Engineer
Sulphuric Acid Recovery, 1911 November 1-1916 June
Sulphuric Acid Recovery, 66 Degree and 84% S. A. Storage, Sulphur and Nitric Acid Recovery and Waste Tower, Sulphur Storehouse, Rebuilding After Explosion. Report by D. T. Rice, Resident Engineer. Photographs by D. T. Rice, W. H. Stevenson
O. V. Storage, 1911 November 28-1916 June
66 Degree and 84% O. V. Foundation and Unloading Crane, Nitric Acid Motor House, O. V. Storage Explosion Rebuilding. Report and photographs by D. T. Rice, Resident Engineer
Mixed Acid Plant, 1912 January 29-1912 March 29
Foundations, Mixed Acid Storage. Report and photographs by D. T. Rice, Resident Engineer
Construction Projects, 1912 February 27-1916 June
Lydol Skids and Heater House, Fuse Magazine. Report and photographs by D. T. Rice, Resident Engineer
View of Plant in Safety Area, 1912 May 30
view from safety area. Report and photographs by D. T. Rice, Resident Engineer
Hatcher and Largent Homestead Move, 1912 July 3-1912 September 3
Moving Largent Homestead, Largent House #5 New Location, Hatcher Homestead, Largent and Hatcher New Location. Report and photographs by D. T. Rice, Resident Engineer
Sales Magazine Construction, 1912 July 30-1912 September 3
Sales Magazine. Report and photographs by D. T. Rice, Resident Engineer
Cottages Construction, 1912 July 30-1912 September 30
New Cottages, Old Cottages, Barn. Report and photographs by D. T. Rice, Resident Engineer
Garage and Stable for Storage, 1912 September 30-1912 November 2
Garage for Storage, Stable for Delivery. Photographs by D. T. Rice
Triton Service House, 1912 September 30-1912 November 2
. Photographs by D. T. Rice
Judson Plant- Various Buildings, 1914 October 26
Dope House, Dope House Conveyor, Dope House Screener, Chain Drive for Screener & Conveyor Belt at Dope House, Coal Grinder, Cooking Bowl, Mixing Bowl and Nitroglycerin Scale Tank. Report and photographs by C. H. Bentley
Project 267, 1916 March 12
Power House Addition. Photographs by W. O. K. Tomes
Project 280, 1916 March 12
Gelatin Cartridge House Barricade. Photographs by W. O. K. Tomes
Project 298, 1916 March 12
Works Laboratory Addition. Photographs by W. O. K. Tomes
Project 283, 1916 March 15
Additional Ammonia Liquor Storage Tank. Photographs by W. O. K. Tomes
Project 304, 1916 March 15
Locker Change House Foundations. Photographs by W. O. K. Tomes
Storeroom- Temporary Construction, 1916 March 15
Construction after fire, Office of Storekeeper and Caprenter foreman, side where fire started, carpenter tool storage, cement storage. Photographs by W. O. K. Tomes
Project 206, 1916 March 15-1916 June
Installing Converter Section, Converter Towers Erected, Blower House. Photographs by W. H. Stevenson, W. O. K. Tomes
Project 299, 1916 March 15-1916 June 15
Increased Soda Storage. Photographs by W. O. K. Tomes, W. H. Stevenson, C. H. Coale,
Absorber and Purification House, 1916 April 24-1916 May 13
A. P. House, Acid Coolers, Tower Pedastals, Absorber Towers. Report and photographs by W. H. Stevenson and H. N. Richardson.